Projects- Current Financial Year (2019-2020)

Description Amount
(in Cr)
% SCP Cost % AS Amount
Total SCP Modules: 43 1538.2
Detailed Project Report 1307.11
84.98%
A/s Accorded 1307.11
84.98%
T/s Issued 1033.17
67.17%
79.04%
Tendered 863.51
56.14%
66.06%
Work awarded 213.66
13.89%
16.35%
Work Completed 174.25
11.33%
13.33%
Expenditure 174.25
11.33%
13.33%



Project Progress ( in INR Cr)

Grant Allocatted Vs Received (in INR Cr)

Total expenditure incurred against Smart City fund allocation (In INR Crores)

Total expenditure incurred against Smart City fund allocation (In percentage)